Challenge

The owner had a very aggressive 24-month production schedule for this 10-story student housing project to ensure it would be ready for the Fall 2020 semester.

ASC Solution

Because the deep foundation work encountered challenges it was completed in 30 days putting the project immediately behind schedule. This required ASC’s Project Team to develop a plan to accelerate the concrete structure schedule. The solution was to use two crews on levels 3 through10. With only one crane planned for this project, ASC had to carefully coordinate work between the two crews as well as plan the daily delivery logistics down to the minute to ensure an on time completion.