Seminole Hard Rock Casino & Hotel East Tower
Tampa, FL
Traditional Form & Turnkey Frame
Service
Traditional Form & Turnkey Frame
General Contractor
Suffolk-Yates Joint Venture
Owner
The Seminole Tribe of Florida
Challenge
Meet a very ambitious production schedule to help the customer capitalize on high guest demand for their peak season and maximize the Casino’s revenue potential.
ASC Solution
While already working on a compressed schedule, ASC found ways to reduce the project duration logistically and methodically by using a column-hung formwork system which eliminated the need for re-shores. This provided a faster turnover of every floor and advanced the turnover of the casino floor by months.
In addition, since staging and laydown areas were not available on the project site, ASC developed an engineered staging plan for the adjacent parking garage. This allowed ASC to build its column-hung tables in advance of going elevated.