Top

Seminole Hard Rock Casino & Hotel East Tower
Tampa, FL

Traditional Form & Turnkey Frame
Service

Traditional Form & Turnkey Frame

General Contractor

Suffolk-Yates Joint Venture

Owner

The Seminole Tribe of Florida

Challenge

Meet a very ambitious production schedule to help the customer capitalize on high guest demand for their peak season and maximize the Casino’s revenue potential.

ASC Solution

While already working on a compressed schedule, ASC found ways to reduce the project duration logistically and methodically by using a column-hung formwork system which eliminated the need for re-shores. This provided a faster turnover of every floor and advanced the turnover of the casino floor by months. In addition, since staging and laydown areas were not available on the project site, ASC developed an engineered staging plan for the adjacent parking garage. This allowed ASC to build its column-hung tables in advance of going elevated.